What is a Payment Schedule? What Components Need to be Included to be Valid?
The Building and Construction Industry Security of Payment Act 2002 (Vic) (‘SOP Act’) plays a crucial role in ensuring prompt and fair payments in the construction industry. Among its key provisions is Section 15, which outlines the process for responding to a payment claim through the submission of a payment schedule. In this article, we will delve into what a payment schedule is, the essential components it must include to be considered valid, and the consequences for both claimants and respondents in various scenarios.
What is a Payment Schedule?
A payment schedule is the formal response served by a respondent to a payment claim under Section 15 of the SOP Act. It is a critical document that outlines the respondent’s position on the claimed amount and must adhere to specific requirements to be considered valid.
Components of a Valid Payment Schedule:
To be considered valid, a payment schedule must include the following components:
- Identification of the payment claim to which it relates.
- Indication of the amount the respondent proposes to pay (scheduled amount).
- Identification of any amount alleged to be an excluded amount.
- Compliance with the prescribed form and inclusion of any prescribed information.
- Clear reasons if the scheduled amount is less than the claimed amount, including the respondent’s justifications for withholding payment.
Timing and Consequences of Providing a Payment Schedule:
According to the SOP Act, a payment schedule must be provided within 10 business days of receiving a payment claim or earlier if specified in the contract. Failure to provide a payment schedule within the stipulated timeframe makes the respondent liable to pay the claimed amount on the payment due date.
It is crucial for respondents to avoid the common mistake of delaying their response beyond the tenth business day, as service on business day 11 renders the payment schedule invalid. Keeping a record of the time, date, and manner of service is recommended to ensure evidence in case of disputes regarding receipt.
Options for Claimants Based on the Respondent’s Payment Schedule:
- Accept the reasons given by the respondent and wait for the scheduled amount to be paid by the due date.
- Apply for adjudication of the disputed amount within 10 business days after receiving the payment schedule.
- Pursue legal action through court proceedings or other dispute resolution processes allowed by the contract.
Non-Payment or Failure to Provide a Payment Schedule:
If a respondent fails to provide a payment schedule and does not pay on time, the claimant can take the following actions:
- Pursue legal action in court to enforce payment as a debt.
- Apply for adjudication to resolve the payment dispute.
- Suspend work or the supply of goods and services under the contract until payment is made.
- Vic Carpet missing authorities, Sent Docusign and cc’d you in the Docusign so you can go through it with the client
- Aref Rezayee missing a cost agreement
- Amir is missing a Trust Account Authority (sent previously on Docusign, will resend it if you like)
- Zaki Azad missing TA authority (sent via Docusign)